DATE: September 16, 2003
TO: Winnefox Library System Board
FROM: John V. Nichols
RE: 2004 Proposed Winnefox Library System Budget
The text of this memo is similar to
what you saw at our last meeting since no changes have been made in any of the
budgets since then. The primary changes
are in the section on WCTS since that was not complete at that time. Im very pleased to report that the net
result of all the following budget changes is that:
The combination of enhanced revenues in some key places, much tighter budgeting in a number of accounts, and judicious cutting have allowed us to balance the 2004 budget without significant service cuts.
WINNEFOX 2004 BUDGET
REVENUES
State Aids - as you know, our state aids for 2004 and 2005 are
expected to show no increase. I think
that is likely to stand since both the Governors and Legislative version of
the budget agreed on this item.
Interest Revenues continue to decline.
Were projecting $11,000 less in Winnefox interest revenues for 2004 due
to declining interest rates and reduced fund balances.
Contractual Revenue, Electronic Services OPL contracts for 50% of the time of Electronic Services
staff. During 2002, that represented
half of two full time positions. As
part of the 2003 budget, we eliminated one of those two positions. For 2004 I have restructured the remaining
staff configuration. Joy Schwarz, ILL
Librarian spends half of her time on web development/electronic service
development projects and has for several years. I have added half of her time to the ESS staff
configuration. OPL will still contract
for 50% of the combined time of this staff which results in a revenue increase
to Winnefox of $17,692.
EXPENDITURES
Salaries & Fringe Benefits we have included an estimated 2% salary increase for all
salaried staff; a 10% estimated increase in health benefits costs; and the
projected increase in state retirement costs.
WALS Coordinator several years ago I had decided that part of Karen
Boehnings cost would be charged to Winnefox since there were many libraries
not in the WALS consortium that would still require her services/support in the
technology area. 25% of those costs
were part of the Winnefox budget.
Since, as of early 2004, there will only be 4 libraries that are not part
of WALS, I have decided to reduce that subsidy to 12.5%. That represents a savings to the Winnefox
budget of $10,609.
Community Relations/Marketing the funds for this position are now included as a
contract in the Contractual Services budget at $45,000 which is approximately
the same cost as the former position (salary and benefits). After discussions with three possible
service providers, we are contracting with Blue Door Consulting to develop a
strategic marketing plan for OPL and Winnefox and then advise us on the best
staff/contractual configuration to carry out those responsibilities.
We have carefully reviewed and
tightened up a number of budget items for some significant savings. One result of this budget tightening is that
we may have to rely on contingency funds more (from our undesignated reserve)
if revenue or expenditure estimates prove wrong.
Telephone reduced by $1,250 based upon past expenditure patterns.
Travel all staff and trustee travel accounts were reviewed and
past experience suggested we could cut them by $7,700 and not have any adverse
impact.
Advertising is used primarily for ads for hiring. Since this happens infrequently, it is a
good candidate for use of undesignated carryover funds if we have to place
ads. Cut $1,000.
Software cut by $2,000 based upon closer scrutiny of past expenditures.
Postage Equipment Expense - cut by $2,000 based upon closer scrutiny of past
expenditures.
Van Replacement we increased this line item by $4,000 in anticipation of
the fact that we will probably need larger vehicles when we replace the present
vans at a higher cost. Half of this
increase comes in as revenue since one van is paid for by WALS member
libraries.
Electronic Information Site Licenses this is perhaps the most direct service cut in this
budget. We will reduce spending on site
licenses by $10,000 and go from $50,000 to $40,000 for 2004.
ILL Net Lender is up due to an increase in net lender volume from the
Resource Library. The rate for ILL
transactions remained the same.
Workshop Registration Reimbursement this line item was eliminated since no expenses had been
charged to it in two years. We
determined it was a redundant line item and that these expenses were being
charged elsewhere. Saves $1,400.
Kay Swan Grants these small education matching grants were increase by
$250.
Staff Training this line item was where we were charging the costs of
computer related training from an allocated reserve established two years ago
for all member library staffs. Since
this was intended as a one time project (which lasted two years), we were able
to substantially lower this line item by $6,500 and still leave $1,500 for
actual staff training.
WALS Membership Fee I lowered this fee by reducing the amount we were
budgeting for PC replacement. We will
draw down our direct capital reserve account for PC replacement for the next
couple of years and rebuild an income stream when state aids revenues increase
again. This saved a net $3,723.
Enrichment Grants this is actually a vestige of cuts made in the 2003
budget. Instead of eliminating the
grants entirely in the 2003 budget, we decided to phase them out and budget
half of the normal amount to be paid out of carryover funds (which is why our
undesignated reserve balance is down over $30,000 this year).
WINNEFOX AUTOMATED LIBRARY SERVICES this budget proposal was reviewed and unanimously
approved by the WALS Executive Committee on July 8, 2003.
Here are the most significant changes
within the 2004 proposed WALS budget.
Formula this is by far the biggest change in the 2004
budget. With the addition of Fond du
Lac to the group of member libraries, the formula allocations for the existing
members decrease enough to cover a number of cost increases so that no existing
members see any significant increase as a result of the upgrade or addition of
Fond du Lac.
Personnel & Operations this line item covers that portion of the WALS staff
funded by the members and associates as well as contracted positions at OPL for
database maintenance (cataloging) and system support. In general, this item reflects the same 2% estimated salary
adjustment and 10% estimated health benefit cost increase as in the Winnefox
budget.
WALS Coordinator as mentioned in the Winnefox narrative, the share of this
position paid for by WALS libraries increased from 75% to 87.5%. I anticipate that this position will
gradually become 100% WALS funded. This
resulted in a WALS budget increase of $10,609.
Catalog Position (.5 FTE) we have added a half-time catalog librarian to the OPL
cataloging operation in order to better manage the addition of Fond du Lac work
load. All WALS libraries share the cost
of this position. Results in a budget
increase of $25,690.
Maintenance this item increases significantly by $49,836 primarily
due to three reasons: 1) an increase in user licenses from 140 to 280; 2) the
addition of Fond du Lac PL to the shared system; and 3) an increase in the cost
of the Syndetics software license since this is now being purchased on a
system-wide basis (it was being purchased by Oshkosh Public Library).
Telecommunications the increase of $9,810 is due to WISCNET charges (our
Internet service provider) being paid fully by Winnefox with no anticipated
e-rate offset. The result of this
action is that no funds would be used by WALS that would require filtering
under the CIPA decision.
Capital Reserve we have begun budgeting again for a gradual build up of
shared capital reserve funds. We
provided everyone a holiday from this expense in 2003. We need to rebuild our shared reserve since
we will be spending it down by over $257,000 during 2003/4 for the SIRSI
upgrade. We have included an increase
to $20,000 in 2004 and will need to gradually rebuild that amount to about
$50,000 a year in order to have enough funds available to upgrade/replace
shared equipment in the future. There
is also $5,000 budgeted for van replacement.
WINNEFOX COOPERATIVE TECHNICAL SERVICES - this budget proposal was reviewed and unanimously
approved by the WCTS Executive Committee on July 8, 2003.
County Contracts in general terms, WCTS is receiving about the same amount
of funding as it received this year with slight variations in the amounts from
each county.
Personnel there are no significant changes in the personnel area.
Contractual Services decreased most in the area of WCTS share of WALS costs
due to the participation of Fond du Lac PL in the formula.
Capital Expenditures none projected at this time.
Staff Training & Travel have been reduced substantially since Mark Arend is no
longer assigned to that budget.
Rotating Collections while these are largely rotating collection circuits
supported by member library dues, there has been some subsidy by Winnefox. It was always anticipated that the subsidy would
gradually decline over several years, and that is what is happening with Large
Print.
There are no other significant changes
in this budget.